Bankside Yards
July 2020 Bankside Yards Progress Update

July 2020 Bankside Yards Progress Update

03/07/2020 by Buildington

Main contractor McGee has achieved a new milestone for the company at the Bankside Yards site. The concrete pour completed this month set a new company record for a single, continuous pour.



1,615m3 of concrete was placed at Basement Level 2, to complete the 3m deep basement raft slab beneath the central building on the site. McGee used 4 pumps to place 215 loads of concrete in just under 12 hours.
 